Hurontario LRT fails to meet fall 2024 completion—major problems with already laid track as construction group’s credit rating downgraded

Mississauga’s already late Hurontario LRT project is now “incurring concurrent delays on multiple other fronts,” according to a recent credit rating report that highlights some of those “multiple” problems. The “project has discovered issues with track tolerances for already installed sections that are out of compliance with specifications.” The credit downgrade report by S&P (Standard […]